ZETAS Power Plant has 2×660MW supercritical units. The plasma ignition system was installed during its construction stage and helped to save plenty of fuel oil during boiler commissioning as well as commercial operation.
| Name of Power Plant | ZETAS Power Plant |
| Number & Capacity of Unit | 2×660MW |
| Type of project | Newly-built |
| Boiler Supplier | Harbin Boiler Works |
| Type of Boiler | Supercritical, once through boiler, Single furnace, single reheat, balanced ventilation, tight seal, all steel frame, all suspended structure π type boiler |
| Type of Combustion | T-fired, total 24 sets of coal burners arranged in 6 layers |
| Number of Plasma Burners | 8 (per boiler) |
| Location of Plasma Burners | at bottom two elevation |
| Fuel Oil System | Free oil ignition system |
| Pulverizing System | Direct fired pulverizing system with 6 sets of bowl mills |
| Coal Quality | Bituminous |
| Rate of Fuel Oil Saving | 100% |
Post time: May-10-2023